Ethermac Exchange-Solar Plans for a Mined Kentucky Mountaintop Could Hinge on More Coal Mining
Will Sage Astor View
Date:2025-04-10 01:53:08
A plan to turn a played-out coal mine into the largest solar farm ever built in Kentucky stirred the imaginations of clean energy advocates with a vision of hundreds of thousands of panels glinting on Ethermac Exchangea thousand-acre wasteland, delivering clean energy to the power grid.
But a year after it was proposed, the $150 million project on Bent Mountain in Pike County, the heart of the state’s eastern coalfield, is still just a vision. Thanks to foot-dragging by Kentucky Fuel, a coal company that is years behind in a nearby cleanup that must come first, time may be running out for the solar venture.
“There is an urgency all the way around,” said Adam Edelen, one of the solar farm’s developers. “We feel it. This project being shovel ready in 2019 or 2020 is really important.” After that, federal tax breaks for renewable energy start to dwindle, undermining the economics.
“If Kentucky Fuel would do what they said they would do there wouldn’t be a problem,” said Edelen’s Kentucky partner, Ryan Johns, vice president of RH Group.
Four years ago, settling one of the largest enforcement actions in Kentucky’s recent history, the coal company’s owners promised state officials that they would compete a tangle of reclamation work spread over several counties by September 2015. But the case has dragged on in court. It’s a fight that involves one of the most powerful families in the region, headed by Jim Justice, the billionaire coal baron who is now governor of West Virginia.
It turns out that the shift from one of the dirtiest fuels to one of the cleanest can be a trickier business in coal country than in, say, corn country.
And in an ironic twist, both sides say paying for this transformation probably depends on digging up more coal where most of a mountaintop was already scraped away.
Unlikely Partners Join Forces on a Solar Farm
The solar project is a joint venture between unlikely bedfellows—EDF Renewables, an international developer of solar and wind energy, and Berkeley Energy Group, a coal mining subsidiary of the RH Group that is interested in diversifying. Berkeley is getting the land ready and works with Edelen, who developed the original concept with Berkeley and is working on finance and marketing.
Electricity from the 100-megawatt array would flow into the regional grid, but who would buy it—they’re looking for a big corporation—isn’t yet known.
“Our ideal will be a company that understands renewable energy is the future and a company that has a social impact value system,” says Edelen, a former state auditor.
Part of Edelen’s sales pitch, delivered in his mild Southern accent, is the solar farm’s location on a former mountaintop-removal coal mine in a part of the country where people are less likely to accept mainstream climate science, and where thousands of jobs have been lost as the nation has turned away from coal.
“The country needs people who sound like me talking about sustainability and climate change, and we need the environmental community to feel the urgency to rebuild coal country,” Edelen said. That includes green-minded companies.
“So many corporations are claiming the mantle of environmental leadership. This is a concrete way to do it,” he said.
Delays by Jim Justice’s Kentucky Fuel
Despite the setbacks, the developers still hope to begin construction by early 2019.
“This can be a speed bump, but it’s not a challenge we cannot overcome,” said Johns.
But Johns said he’s frustrated that a Justice family mining company, Kentucky Fuel, is years behind state-imposed deadlines to complete required reclamation work, including at a location near the proposed solar farm.
Kentucky Fuel’s attorney, Richard Getty, blames state regulators for slowing down the reclamation.
He filed a lawsuit last year claiming that the regulators, who were seeking to collect millions in fines from the Justice companies, chased away a mining and reclamation contactor with unspecified “willful and malicious” comments. The suit went after the personal assets of two state mining officials. Their agency, the Kentucky Energy and Environment Cabinet, called the lawsuit meritless. It remains unresolved.
Without going into details, Getty said reclamation work could resume soon.
The sooner the better, in the view of both the solar developers and the state officials.
What It Means to ‘Reclaim’ Bent Mountain
In 2014, Jim Justice reached a settlement with the Kentucky Energy and Environment Cabinet involving hundreds of reclamation violations in several of the state’s eastern counties. He agreed that by September 2015 his companies would reclaim 10 miles of what are known as “high walls”—what’s left standing after mountains are blasted to expose coal seams. Three miles of these have yet to be finished—including 2,700 feet of Bent Mountain, at a spot near the proposed solar farm.
John Mura, a spokesman for the state environment cabinet, said that one way or another, the Bent Mountain high wall needs to be restored to its approximate original contour.
That means bringing down the exposed walls, eliminating waste rock piles and restoring a landscape similar to what was there before, according to Kentucky regulations.
“We have been pushing Kentucky Fuel to reclaim that, and they have not done so,” Mura said. “And that’s one of the reasons we will be back in court on June 11.”
According to Johns, most of the high wall’s 2,700-foot-long face is on land abutting the solar site, and their fates are closely linked.
For one thing, the solar farm is designed to use rubble from reclamation to flatten out its own contours. For another, repairing the high wall involves more blasting, too close to allow the fragile panels to be installed until after it’s over.
More Coal Mining?
Kentucky Fuel wants more mining to help pay for the work.
“Other people might be interested in coming in there and doing some additional mining and reclamation,” said Getty, the lawyer for Kentucky Fuel. That’s a standard practice when there’s still coal available for recovery and it can be sold to help pay for the reclamation, he said. And the new waste rock gets used to re-shape the land.
But it is not clear whether valid leases are in place for that approach. That, too, may have to be sorted out; if not, the state could issue a permit for reclamation only, but the work would be more expensive.
It’s unclear whether the costs of additional reclamation, and the possibility of paying for it with more mining, would materially affect the solar farm’s construction costs. Delay itself can be costly in this kind of project, as state and federal incentives change.
“We are doing everything we can to make it as competitive as possible,” said Doug Copeland, who works in Philadelphia as regional development manager for EDF Renewables. “We are still very excited about it. My hope is that sometime later this year, we’ll have some real news on the project.”
The proposal “sounds like it would be of interest to companies that want to procure renewable energy if the price is right and if they want to tell a story of helping communities transition away from coal,” said Dan Bakal, director of electric power at Ceres, a Boston coalition of businesses and environmental groups.
“But it comes down to getting the price right to where it competes well with other projects that are out there,” he said.
veryGood! (5943)
Related
- Average rate on 30
- Modern Family’s Ariel Winter Teases Future With Boyfriend Luke Benward
- If you let your flood insurance lapse and then got hit by Helene, you may be able to renew it
- After Hurricanes Helene and Milton, Bacteria and Chemicals May Lurk in Flood Waters
- 2 killed, 3 injured in shooting at makeshift club in Houston
- Woman who stabbed classmate to please Slender Man files third release request
- 'It's relief, it's redemption': Dodgers knock out rival Padres in NLDS with total team effort
- Pilot in deadly California plane crash didn’t have takeoff clearance, airport official says
- Biden administration makes final diplomatic push for stability across a turbulent Mideast
- Alabama corrections officer charged with smuggling meth into prison
Ranking
- Juan Soto to be introduced by Mets at Citi Field after striking record $765 million, 15
- Notre Dame-Stanford weather updates: College football game delayed for inclement weather
- Nevada high court to review decision in ex-Raiders coach Jon Gruden’s lawsuit over NFL emails
- Tampa Bay Times keeps publishing despite a Milton crane collapse cutting off access to newsroom
- Whoopi Goldberg is delightfully vile as Miss Hannigan in ‘Annie’ stage return
- The 2025 Ford Mustang GTD packs more HP than expected — at $325K
- Texas man held in Las Vegas in deadly 2020 Nevada-Arizona shooting rampage pleads guilty
- Colorado has become Coach Prime University, sort of. Not everyone thinks that’s OK.
Recommendation
Rylee Arnold Shares a Long
Kylie Jenner Shares Proof Big Girl Stormi Webster Grew Up Lightning Fast
Ex-US Army soldier asks for maximum 40 years in prison but gets a 14-year term for IS plot
Trial on hold for New Jersey man charged in knife attack that injured Salman Rushdie
Arkansas State Police probe death of woman found after officer
IRS extends Oct. 15 tax deadline for states hit by hurricanes, severe weather
Children and adults transported to a Pennsylvania hospital after ingesting ‘toxic mushrooms’
Why 'Terrifier 3' star David Howard Thornton was 'born to play' iconic Art the Clown